ADU Permit Assistance in Bakersfield: How the Process Works
In Bakersfield, an accessory dwelling unit (ADU) needs two approvals in a set order: a planning approval, then a building permit. The paperwork is the part that stalls most projects. The best help is a builder who handles city permits as part of the build. At IC Revamp Construction, we manage everything from city permits to custom carpentry on ADU projects, so the application, the corrections and the inspections do not become your second job.
An ADU is a small, self-contained home on the same lot as your house: a backyard cottage, a garage conversion, or a unit attached to the main home. This guide walks through what Bakersfield and California require, what it costs at the permit stage, how long it takes, and where applications go wrong.
Key Takeaways
- Bakersfield reviews an ADU in two stages: Site Plan Review (planning) first, then the building permit. Budget for both.
- State law limits cities to objective standards and sets deadlines. The city must tell you in writing within 15 business days whether your application is complete.
- Permit-stage costs vary widely. The city’s fee schedule lists an ADU application fee of $554.00, and Site Plan Review fees from $1,260 to $12,307 depending on the project.
- Most delays come from incomplete documents and site conflicts, not from the law. A complete first submittal is the cheapest way to save time.
- Permit handling is part of what we do on ADU builds, alongside design, coordination and construction.
Table of Contents
- What “ADU permit assistance” actually covers
- The Bakersfield ADU process, step by step
- What state law means for your application
- Fees and timelines at the permit stage
- Why applications get delayed, and how to prevent it
- Money that can offset permit-stage costs
- Our point of view
- Talk to us about your ADU
- FAQ
- Sources
What “ADU permit assistance” actually covers
The phrase covers three different kinds of help, and it is worth separating them.
Public information. Bakersfield publishes a free ADU Guidebook, an ADU Standards Plan Gallery with pre-reviewed plans, a cost calculator, a GIS mapping portal to check your property and utility requirements, and a free consultation with a city planner, all described on the city’s ADU process page. The state also runs an ADU portal through HCD, the California Department of Housing and Community Development, for technical assistance requests.
Document preparation. Someone has to produce the site plan, elevations, floor plans and landscape plans that the city asks for, and keep them consistent with each other.
Submittal and follow-through. Someone has to file online, answer corrections, pay the fees, pull the permit and schedule inspections.
The city’s resources tell you what the rules are. The second and third jobs are where the hours go, and that is the work we take on when we build your ADU. Our ADU service is built around handling that chain from design through the finished unit.

The Bakersfield ADU process, step by step
The city lays out ten steps on its official process page. Here they are in order, with what each one involves and where it tends to go wrong.
1. Learn the rules and check your lot
Start with the city’s guidebook, the plan gallery and the GIS mapping portal. The portal shows your property and utility information. Setbacks (the required distance from property lines), easements and utility locations decide what fits on your lot before any design begins.
2. Sketch the unit and talk to a planner
A rough sketch of where the unit goes and how big it is lets a city planner give you useful advice. The consultation is free. Where it goes wrong: bringing a sketch that ignores an easement or a height limit, which only surfaces later as a correction.
3. Assemble the design and build team
The city’s process calls for a licensed architect or designer and a builder. With us, the design and the build are not separate hand-offs: we offer virtual 3D CAD design, so you can see the unit before the plans go to the city, and we coordinate the project start to finish.
4. Submit the Site Plan Review (planning application)
This is the planning stage, filed online. According to the city’s ADU Toolkit, the submittal includes:
- a site plan, elevations and floor plans
- landscape plans in higher-density zones
- an Indemnification Agreement
- a Property Owner Authorization form, if the applicant is not the owner
- the fee
The city’s Site Plan Review checklist adds that each document is uploaded individually, and that you must show how the ADU is architecturally compatible with the main house, using elevation drawings or photographs of the existing residence. Planning review is described as taking up to 30 working days.
5. Submit the building permit application
After planning approval, you file the building permit application with construction documents and the Planning stamp of approval. The city runs a prescreen, then department reviews. Construction documents are technical: structure, energy, plumbing and electrical details must match the approved site plan.
6. Pay final fees and pull the permit
Once the reviews are cleared, you pay the final fees and receive the permit. The city says the permit is valid for one year.
7. Build
The city’s page notes that construction commonly runs 12 to 18 months, and the ADU Toolkit estimates construction at 2 to 12 months, so plan around the specific scope of your unit rather than one number.
8. Final inspection and Certificate of Occupancy
The last step is scheduling the final inspection by calling 661-326-3720. A Certificate of Occupancy is required before anyone lives in the unit, as stated in the state’s ADU Handbook (March 2026).

A step the law gives to the city, such as plan review and inspection, is part of the process for every builder. What differs is who prepares the submittals, answers the corrections and keeps the schedule moving. On our projects, that is us.
What state law means for your application
California’s ADU rules set the frame that Bakersfield works within. Four points matter to a homeowner:
- Ministerial approval. The HCD handbook defines this as approval without discretionary review or a hearing, and says local agencies may impose only objective standards on ADUs.
- Completeness deadline. The agency must decide whether your application is complete and give written notice within 15 business days of receipt. If it misses the deadline, the application is deemed complete.
- Appeals. After a written appeal of an incomplete or denied application, a final written determination is due within 60 business days.
- Environmental review. ADUs approved ministerially are statutorily exempt from CEQA, the California Environmental Quality Act.
For an ADU of up to 800 square feet, HCD’s October 2025 letter to Bakersfield describes the state requirement that a permit be approved, while local agencies may designate areas based on water and sewer service, traffic flow and public safety. The city’s own code states that its ADU chapter is meant to allow ADUs consistent with state Government Code provisions.
One more point for owners of older, unpermitted structures: the same handbook states that permits for unpermitted ADUs built before January 1, 2020 cannot be denied for building-standard or ordinance violations unless health or safety findings are made.
Projects that exceed the city’s standards, for example in size or height, may need a Special Permit with additional review and possibly a public hearing, according to the city’s ADU FAQ. Designing within the standards from the start avoids that.
Fees and timelines at the permit stage
The City of Bakersfield’s fee schedule, published July 2025, is the document to check. It lists:
| Item | Amount per the July 2025 schedule |
|---|---|
| ADU application fee | $554.00 |
| Site Plan Review fees | $1,260 to $12,307, staff-calculated |
The schedule notes that the fees cover items such as public hearing, environmental processing and posting, California Department of Fish and Wildlife charges and administrative costs. Fee schedules are updated, so confirm the current figures with the city before you budget.
Two other costs surprise owners:
- School fees apply to ADUs of 500 square feet or more and are assessed by square footage. The Kern Superintendent of Schools (661-636-4000) or the city Building Department (661-326-3727) can confirm the district and current fees.
- Utilities. New or separate connections may be required, and the city advises contacting PG&E early.
On timing, the city’s Toolkit estimates permitting at 1 to 6 months and construction at 2 to 12 months. That range is wide because it depends on how complete the first submittal is and how many correction rounds follow.
Why applications get delayed, and how to prevent it
The usual causes of delay or denial are practical, not legal:
- Incomplete documents. A missing form, a plan that does not match another plan, or an elevation that does not show the existing house.
- Setback and size problems. A unit placed too close to a property line, or one that exceeds size, height or lot-coverage standards.
- Utility easements and site conflicts. Sewer, water or power lines running where the unit is drawn.
- Fire-safety requirements. Some sites carry additional requirements that need to be designed in.
- Private restrictions. An HOA or recorded deed rules can conflict with your plans even when the city approves.
The fix is the same for all of them: check the lot first, design to the city’s objective standards, and submit everything at once. When the city does flag something, answer every item in one resubmittal rather than piecemeal. We plan before we submit: our work is built around a thorough planning phase, with 3D CAD design so layout decisions are made before they become plan corrections.
Structure is one of the technical areas where a unit can be sent back. Wood-framed ADUs need lateral-force design, and this overview of ADU shear wall requirements explains what shear walls are and why the drawings must show them.
Money that can offset permit-stage costs
The CalHFA ADU Grant Program reimbursed qualifying homeowners up to $40,000 for pre-development costs such as designs, permits, soil tests, impact fees, surveys and energy reports, for owner-occupied single-family lots with low or moderate income. HCD’s March 2026 handbook notes the funds were exhausted at the time of writing, so watch for any reopening. The same handbook mentions that FHA, Freddie Mac and Fannie Mae offer ADU loan products, and that some local agencies create their own funding or fee waivers. Ask the city planner what applies to your parcel.
Our point of view
Homeowners rarely struggle with the idea of an ADU. They struggle with the sequence: planning approval, building permit, utility connections, school fees, inspections, and a plan set that has to agree with itself on every page.
That is why we run permits as part of the build instead of as a separate errand. We have completed over 450 projects in Kern County, and we handle city permits, custom carpentry and the coordination between them. Our virtual 3D CAD design lets you see the unit before drawings go to the city, and our fixed-price guarantee means the scope you sign is the scope we price.
We build with dust control in mind and back our work with a five-year labor warranty. For an ADU, the permit is not a hurdle beside the project. It is the first stage of the project, and we treat it that way.
Local
Talk to us about your ADU
If you own a lot in Bakersfield or elsewhere in Kern County and want a backyard unit, a garage conversion or an attached suite, start with a consultation. We will look at your property, the unit you have in mind and what the city will need to see, then take the permit process from there. See our ADU Units page for details.

Our work extends to kitchens, bathrooms and whole-home remodels, so an ADU can be planned together with updates to the main house. You can also see the areas we serve around Bakersfield.
FAQ
Do I need both a planning permit and a building permit for an ADU in Bakersfield?
Yes. The city’s FAQ states that the sequence is a planning permit first, then a building permit. Planning is the Site Plan Review. The building permit follows with construction documents and the Planning approval stamp.
How long does the city have to respond to my ADU application?
Under California’s ADU Handbook, the city must decide whether your application is complete and notify you in writing within 15 business days of receipt. If it misses that deadline, the application is deemed complete. Overall permitting is estimated at 1 to 6 months in the city’s Toolkit.
Do I need a Certificate of Occupancy?
Yes. A Certificate of Occupancy is required before the unit can be lived in. You get it after the final inspection, which is scheduled by calling the city at 661-326-3720.
Are there grants for ADU permit and design costs?
The CalHFA ADU Grant offered up to $40,000 for pre-development costs to eligible owner-occupants, though HCD’s March 2026 handbook says funds were exhausted when written. Loans from FHA, Freddie Mac and Fannie Mae are also available for ADUs, and some cities offer their own fee waivers.
Sources
- The ADU Process, City of Bakersfield
- ADU Toolkit, City of Bakersfield
- Site Plan Review Process and Checklist, City of Bakersfield
- ADU Frequently Asked Questions, City of Bakersfield
- Accessory Dwelling Unit Handbook, HCD, March 2026